we help the
industry
to develop
Wind park project Ongoing
-
S Power has started the development process of a wind power plant with a total installed capacity of up to 144 MW and an efficiency of over 43% (net capacity factor over 37%).
The area where the S Power wind power plant is located - Cherkasy region - is energy-scarce, and emergency shutdown schedules are often applied by NPC “Ukrenergo”. The connection of new powerful consumers (and therefore the economic growth of the region) is out of the question without further development of the region’s energy generating facilities. Therefore, the Project contributes greatly to ensuring energy independence of central Ukraine
-
The Project is in the early stage of the development: feasibility study has been completed; preparations are underway for approval of a detailed plan of territory; permits for the development of land management documentation were obtained from local authorities (for Stage I)
The Project location is very favorably placed in terms of wind resources, energy demand and logistics.
Close proximity to a source of fresh water - the Kremenchug Reservoir as well as to the main gas pipeline of the gas transportation system of Ukraine creates an additional opportunity to produce and transport “green” hydrogen
-
Two stages of project development and construction are planned:
Stage I - 72 MW - construction is to start in the middle of 2025, the plant to be commissioned and launched in Q4 2026
Stage II - 72 MW - construction is to start in Q3 of 2025, the plant to be commissioned and launched in Q1 2027
-
The launch of full 144 MW wind power plant will generate 480 GWh per year, providing “green” electricity to more than 200 thousand households and reducing carbon emissions by over 1.3 million tons annually.
The wind farm is projected to yield an annual revenue of 30 mln euros, with an EBITDA margin of up to 92%, and an equity IRR of up to 23%