S Power is an investment project to build a modern wind power plant with a total capacity of 151.2 MW in Cherkasy region, an energy-deficient region of central Ukraine.

The use of modern technological solutions and world-leading equipment will create one of the largest sources of renewable energy in the country.

The amount of investment in infrastructure. Jobs.

The planned launch of the full capacity of the wind farm is 2028. The project provides for the possibility of further development, in particular the production and transportation of "green" hydrogen.

total power generation
151 MWh
total power generation
power generation per year
500 GWh/y
power generation per year
household coverage
200 + k
household coverage
CO₂ annual reduction
1300 ktons
CO₂ annual reduction
Implementation stages

Construction is planned in three stages

Preparatory work at the enterprise is planned for 2026, with the introduction of the entire design capacity in 2028. The possibility of phased commissioning of each of the 21 turbines is envisaged, which ensures system adaptability and risk reduction.

Stage I

49,5 МВт

Stage II

54,0 MWh

Stage III

49,5 MWh

Concept
Designing
Preparation
Construction
Operation